1 Introduction

1.1 Audience

AEMO Australian Energy Market Operator provides this information as a service targeting business analysts and IT staff in Registered Participant See Relevant Rules or Procedures companies.

The primary audience is NMISP National Metering Identifier Service Provider. Responsible for managing Secondary Settlement Points (SSPs), DNSP Distribution Network Service Provider. A business that owns, operates or controls an electricity distribution network., FRMP Financially Responsible Market Participant, usually a retailer, Generator, Market Customer or a Market Small Generator Aggregator, identified in respect of a connection point. Responsible for dealings with AEMO in relation to a specific load., MC Meter Coordinator; The Role Code used in MSATS for an MC is RP., and MDPs.

1.2 Objective

The MSATS Market Settlement and Transfer Solutions. The procedures published by AEMO under clause 7.2.8 of the National Electricity Rules, which include those governing the recording of financial responsibility for energy flows at a connection point, the transfer of that responsibility between market participants, and the recording of energy flows at a connection point. - Secondary Settlement Points - November 2026 (Release) describes the projects planned by AEMO from a participant perspective and includes any system related changes for participants.

1.3 Status

Version

Status

1.00

In pre-production.

0.07

The design is mostly complete. We expect more changes as AEMO testing and feedback continues. Participants can commence development providing they understand there may be some changes.

0.06

In progress. The design is not ready for participants’ builds.

0.05

In progress. The design is not ready for participants’ builds.

0.04

In progress. The design is not ready for participants’ builds.

0.03

In progress. The design is not ready for participants’ builds.

0.02

In progress. The design is not ready for participants’ builds.

0.01

Initial Draft for review. The design is not ready for participants’ builds

Presents the MSATS - Secondary Settlement Points - November 2026 evolving design.

Please send feedback to techwriters@aemo.com.au

 

1.4 Release dates

Scheduled for implementation in:

1.5 Projects and enhancements

For changes and enhancements for this Release, see High-level changes.

1.6 Rule and procedure changes

Title

Status

Effective

National Electricity Amendment (Unlocking CER benefits through flexible trading) Rule 2024: Schedules 3,4, and 5

Final

1 November 2026

Meter Data Management (MDM) Procedure v4.7

Amendment

1 November 2026

Service Level Procedure Embedded Network Manager Services

Amendment

1 November 2026

Service Level Procedure NMI Service Level Provider v1.0

Draft

1 November 2026

Service Level Procedure MDP Services v2.6

Amendment

1 November 2026

Service Level Procedure MP Services v2.1 

Amendment

1 November 2026

B2B Procedure: Technical Delivery Specification

Amendment

1 November 2026

B2B Procedure: Service Order Process

Amendment

1 November 2026

B2B Procedure One Way Notification Process

Amendment

1 November 2026

National Metering Identifier procedure v7.5

Amendment

1 November 2026

B2B Procedure: Meter Data Process

Amendment

1 November 2026

B2B Procedure: Customer and Site Details

Notification Process

Amendment

1 November 2026

MSATS Procedures - Principles and Obligations for All Connection Points v8.1

Amendment

1 November 2026

Standing Data for MSATS v6.3

Amendment

1 November 2026

Metrology Procedure Part A v8.2

Amendment

1 November 2026

Metrology Procedure Part B v8.2

Amendment

1 November 2026

Qualification Procedure (Metering Providers, Metering Data Providers & Embedded Network Managers)

Final

1 October 2025

Default and Registration Procedure

Final

1 November 2026

1.7 Related technical specifications

Title

Description

MSATS – Technical Specification – May 2026

System changes required for participants to support the implementation of Flexible Trading Arrangements (FTA), including type 9 metering installations

MSATS - aseXML B2M schema r47 - August 2026

New B2M aseXML schema version r47

MSATS - aseXML B2B schema r48 - November 2026

New B2B aseXML schema version r48

EMMS – Portfolio Management System - September 2026

PMS is updated to support the Premises Network Service Provider (PNSP) role and NMI Service Provider (NMISP) roles introduced for Secondary Settlement Point (SSP) arrangements. It also includes validations to support SSPs

1.8 Related documents

These guides and resources are updated according to this technical specification and published for the pre-production Release Date.

Title

Description

Status

aseXML r48 schema

aseXML r48 schema files

Published

B2B Mapping to aseXML

Describes the mapping between the MSATS B2B procedures and the B2B aseXML schema

In progress

B2M Mapping to aseXML

Describes the mapping between the MSATS B2M procedures and the B2M aseXML schema

In progress

Guide to MSATS B2B

Information about the B2B e-Hub functions available in the Market Settlement and Transfer System (MSATS)

In progress

Guide to MSATS Reports

Information about CATS and MDM reports

In progress

Guide to MSATS Web Portal

Information about the B2M functions available in the Market Settlement and Transfer System (MSATS) web portal

In progress

Guide to B2B Validation Module

Describes setting up and using the B2B Validation Module software

In progress

Standing Data for MSATS v6.31

Reference guide assisting participants interacting with MSATS to understand MSATS NMI Standing Data tables

Published

1.9 Related software

Software

Change

Available

B2B Validation Module v1.9

New version updated for aseXML schema r48

Pre-production:
4 September 2026

 

MSATS Participant Batcher

B2B Batch Handlers

1.10 Approval to change

AEMO is seeking Participant feedback from the Electricity Retail Consultative Forum (ERCF Electricity Retail Consultative Forum), B2B Business-to-Business. Generic term used to refer to defined business-to-business interactions between participants; excludes interactions between a participant and market systems such as MSATS. Working Group A group is a collection of one or many roles with permissions. AEMO System Administrator or Participant Administrator can optionally assign specific Groups to the users to simplify the management of users and roles., NEM Reform Implementation Forum, Industry Test Working Group, and interested parties.

1.11 Market systems user group meetings

The Market Systems User A user is a person who uses the system, either through UI (interactive) or by Batch processing (batch). To use the system each user must be associated with a participant ID and a Role. The Role assigned to the user determines the menu options and interfaces the user can access, and what actions (privileges) the user can complete. Group (MSUG Market Systems User Group) is an industry user group established to discuss NEM wholesale and retail IT systems releases. Its purpose is to facilitate the continuing improvement of AEMO's IT systems by seeking feedback and collaboration from participants.

MSUG meetings are open to all interested parties, with invitations sent to all included on the distribution list. If you have a technical question for a project and want to attend the MSUG ask your company’s support team to include your email address in their AEMO Help Desk Bulletin (CRM) distribution list.

1.12 Version numbers

Incremental version numbers such as 1.01, 2.01 and so on mean there is a minor change to the technical specification.

Major version numbers such as 1.00, 2.00 means there are substantial changes to the technical specification. Participants must carefully review these changes, detailed Page 1.

1.13 Changes in this version

This version has the following changes:

  • Adds c1 and c4 report examples.
  • Adds RM29 examples.
  • Adds field names, permitted values and aseXML examples for the Service Order – Update Standing Data transaction.
  • Adds EMMS – Portfolio Management System - September 2026 to related technical specifications